Not a lot to tell at the moment other than it has been raining most of the week and well……RAIN CAUSES DELAYS. Unfortunately we were just a few days away from putting the roof on but we decided to build a small 3rd floor area to use as a conference room and this delayed the roof and then the rain delayed some of the interior construction……..yee gadds…….I don’t like it but what can we do.  Hopefully we can catch up but I am sure that my contractor will have some excuse now not to complete on time but we will keep you posted.

Have added a couple of pics that I took yesterday of the Workspace Floor progress.

By the way, wondering where we came up with the name RAFF’S?  It is from our eight year old genius Rafael Benjamin who proudly walks around telling everyone that he is the owner.