Well, as the title says, we are on Day 3 of Week 16 of the RAFF’S BALI build.  Unfortunately the past two months have been plagued by constant rain exacerbated by the High Holidays in Indonesia – Lebaran / Idul Fitri / Ramadan. So we have about three to four weeks project delay but our illustrious contractor Gianto is doing his best to catch up.

Nevertheless things are shaping up as the picture gallery of this blog will show.  We closed off on structural elements, have nearly closed off on interior construction….toilet block, balustrades, awnings, stairways, kitchen and bar areas, ponds etc and by next week we will start the fitout….(some of it started eg tiles) and then we should see some progress.

We are all excited about this concept and have had great feedback from friends, family, customers and suppliers….all cannot wait.

We will keep you posted.